Grade II Listed Bank Date: Nov 2005 Project Duration: 28 weeks Project Value: 300,000
The entire project was conducted out of hours
with each floor phased into
separate sections.
The existing mechanical plant served all floors
and was non
functional at the beginning of the
project so HSES designed/developed temporary
heating and fresh air to all aspects
of the working environment to assist the client whilst the project was undertaken.
KEY FACTS
Refurbishment of four floors, utilising modern energy initiatives
VRF A/C,
ventilation and control systems installed within existing internal and external
structure meeting with all planning and BCO requirements associated with a Grade
II listed building
Existing mechanical systems/plant stripped out
Bank fully operational during
the project without any interruption
Entire project completed out of hours with
each floor phased into separate sections